TerraTherm - Soil Remediation using In Situ Thermal Desorption (ISTD)

The Worldwide Leader in Thermal Remediation

Company Services Technology Projects Newsroom Resources Home
TerraTherm - Newsroom  


News


News & Events
Press Releases

 

 


 

MGP Gasholder Cleaned without Excavation: Completion of North Adams, MA ISTD Project

 

In June 2005, TerraTherm completed a novel MGP site cleanup under a performance-based contract with National Grid at their facility in North Adams, MA. The site was a former Manufactured Gas Plant (MGP) facility operated by the North Adams Gas Light Company in the late 1800s and early 1900s. A 62-ft diameter by 18-ft deep gasholder tank, located entirely below grade, contained soil, debris, and coal tar, but National Grid had not been able to recover significant quantities of the coal tar and needed to clean the tank to state standards. The usual approach for such sites is to dig them up and dispose of the soil and waste off-site; however, National Grid selected TerraTherm's ISTD technology as less expensive and much greener than excavation. TerraTherm demonstrated that their choice was well justified!


National Grid Site in North Adams, MA, post-treatment


After dewatering the gasholder, TerraTherm applied ISTD to eliminate the dense non-aqueous phase liquid (DNAPL) coal tar and proceeded to remediate the gasholder using a tailored heating approach, thereby achieving soil cleanup standards protective of groundwater, all without excavation.

We first installed 25 thermal wells and employed gentle heating (~80°C) for thermally enhanced DNAPL recovery, producing over 16,000 gallons of coal tar/emulsion. This was significant, as the client had expected us to be able to recover several hundred gallons at the most. We then raised the heating temperatures to attain the project goals, which a risk assessment had determined to be distinctly different above versus below 15 ft depth (the limit of construction worker exposure). Within the mid-section (above 15 ft depth), we achieved temperatures of 615°F to volatilize, boil, pyrolyze and oxidize the Polycyclic Aromatic Hydrocarbons (PAHs). This is our classic ISTD approach. Within the bottom portion of the gasholder (15-18 ft depth), we attained more moderate temperatures of 212°F (the boiling point of water) to remove the DNAPL. In the process we vaporized the benzene and naphthalene from the entire gasholder. Overall the extracted vapor contained 165,000 lb expressed as naphthalene, which we treated in an aboveground thermal oxidizer to meet the required air emissions standards.

Within the mid-section of the gasholder, elevated heating produced the following significant reductions in soil concentrations (mg/kg) that more than met the required standards at the site: benzene - 2068 to 0.35; naphthalene - 679 to 5.7; and benzo(a)pyrene - 20 to 0.33. Within the lower portion, more moderate heating was sufficient to remove all the DNAPL, as required. In fact the residual material looked much like asphalt - it was dry, brittle, and the benzene and naphthalene concentrations were reduced by over 99.5%! National Grid judged the turnkey cost ($850,000 for ISTD) to be less than the excavation alternative. TerraTherm conducted the project under a guaranteed performance contract, meeting all the remedial goals. We will co-present these results with our National Grid client at the upcoming MGP2006 Conference in Reading, UK in April 2006, and at the Battelle Monterey Conference in May 2006. Please contact us to see how we can apply our tailored heating approach to your MGP site!